Case study · AMAZIN Automation Solutions · 2024–26RECOVERED

Turning around a critically delayed go-live in 25 days

How I took a FIRLO go-live that was 4 months late to live in 25 days, avoided a penalty and kept the client for more sites.

  • Turnaround
  • Risk management

Context

At AMAZIN Automation Solutions, a FIRLO go-live at a cement plant was 4 months behind schedule. The project was weighbridge automation.

What had gone wrong

  • The site wasn’t ready for installation.
  • The requirements weren’t clear.
  • The client had escalated, and there was a real risk of a penalty.

What I did

I reset the plan and worked through everything that was blocking go-live:

  • Ran a workshop with the client to get the requirements clear and agreed.
  • Got the site ready, working through every open readiness item.
  • Checked every piece of hardware, and replaced or repaired anything that wasn’t usable.
  • Set up a daily checklist and gave each task a single owner.
  • Sent the client an update every day and agreed a new go-live date.

Outcome

  • The site went live 25 days later, on the new date we had committed to.
  • No penalty. The project moved from red to green.
  • The client rolled out more sites with us afterwards.